Power
158 MW
Overview
AirTrunk's Sydney North campus expanded to 158MW+. 70MW expansion completed Sept 2024 in 35 weeks.
Key Points
- •158MW+ capacity across multiple buildings
- •4.2ha with 29,000 sqm technical area, 24 data halls
- •Phase 1 (2021), Phase 2 (2023), Phase 3 (Sept 2024)
- •70MW expansion completed in 35 weeks
- •Dedicated 200MVA 132kV substation
Development Details
Land Size
10.4 acres
Spec Sheet (PDF)
Mar 2026