Overview
Located in southwestern Vienna with 20MVA power supply and underwent expansion in 2022 adding 3,000 square meters.
Key Points
- •15.2MW IT capacity with 8,500m² of server space opened in 2015
- •20MVA total power supply with 1.8-2.0kW/m² average power density
- •Expansion completed in summer 2022 adding 3,000m² bringing total to 8,600m²
- •Located 6km from Vienna city center and 20km from Vienna International Airport
- •Includes 1,000m² of offices and conference space beyond data center services
Certifications
Tier 3-TIA 942/GISO 9001ISO 27001ISO 50001PCI DSS
Infrastructure
UPS Redundancy
2N