Microsoft AzureOperational
Microsoft Grange Castle Campus
Grange Castle Business Park, Dublin, Ireland
Est. 2009
Power
170 MW
Colocation Space
605.0K sqft
Overview
Microsoft's first data center outside the US, commissioned 2009. Now expanded to 6+ buildings including DUB5, DUB9-15 with ~239MW campus.
Key Points
- •~239MW campus capacity - Microsoft's first outside US
- •Commissioned 2009, now 6+ buildings (DUB5, DUB9-15)
- •DUB5: 25.6MW, DUB11: 16MW individual buildings
- •16 gas generators providing 18MW backup
- •19-acre original site in Grange Castle Business Park
Spec Sheet (PDF)
Mar 2026
Sources: