Google Port Dickson

Springhill Industrial Park, Persiaran Springhill, 71010 Port Dickson, Malaysia, Port Dickson, Malaysia
Google Cloud Locations
Power

850 MW

Overview

Part of Google's $2B Malaysia investment. 389 acres acquired from Gamuda, infrastructure work 2025-2028.

Key Points

  • 389-acre site acquired from Gamuda for ~$107M in May 2025
  • Part of Google's $2B investment in Malaysia's digital infrastructure
  • Expected capacity 500MW to 1GW based on industry estimates
  • Located 90km south of Kuala Lumpur along Malacca Strait
  • New water treatment plant (65M liters/day) and pipelines included
  • Infrastructure completion phased: 2025, 2027, 2028
  • Gamuda as development partner (also handling Google's Elmina site)

Development Details

Land Size

389 acres

Timeline

Land Acquired:May 2025