GreystokePlanned

Greystoke West London Tech Park Building 1

Iver, United Kingdom
Greystoke
Power

45 MW

Colocation Space

387.5K sqft

Overview

Greystoke West London Technology Park Building 1 in Iver, Buckinghamshire. Part of 90-96MW campus (two buildings, 775,000 sqft). Planning approved July 2025 after government overruled council. £1B+ investment.

Key Points

  • Part of 90-96MW campus in Iver, Buckinghamshire on M25
  • Two buildings totaling 775,000 sqft with new substation
  • Planning approved July 2025 - government overruled Buckinghamshire Council
  • Former landfill site on Green Belt
  • £1B+ inward investment, ~230 operational jobs
  • Part of Greystoke's 2.5GW UK pipeline

Development Details

Total Investment

$1B

Buildings (Planned)

2

Total Space (Planned)

0.8M sqft