Overview
Second building at EdgeCore's Mesa campus. Topped out Dec 2024. Campus supports 450MW+, $1.9B green financing secured.
Key Points
- •32 MW per building (campus design spec)
- •140,000 sqft per data center
- •Topped out December 2024
- •Campus: 3.1M sqft, 450+ MW capacity
- •$1.9B green financing for campus
- •LEED designed, Green Globes certified