DCQ
Stream Data CentersUnder Construction

Stream Phoenix II

Goodyear, Phoenix, AZ
Stream
Power

40 MW

Overview

Stream's second Phoenix building at Goodyear campus. 40MW, 157-acre campus expandable to 280MW.

Key Points

  • 40MW per building
  • 157-acre campus
  • 480MW dedicated APS substation
  • 280MW at full build-out
  • 2 million sq ft planned
  • Topped out August 2024

Certifications

ISO 27001SOC 2
VerifiedSource: Stream
Mar 2026