STACK SVY02A in Santa Clara on former Memorex HQ. 551,000 sqft, 48MW with dedicated substation and 8 data halls. Currently awaiting full power from Silicon Valley Power (2028 grid upgrade).

Key Points

  • 551,000 sqft building with 4 floors of data halls
  • 48MW capacity with dedicated on-site substation
  • 8 data halls, 12MW immediately available for lease
  • Built on former Memorex headquarters site
  • Awaiting SVP grid upgrade ($450M project, completion 2028)
  • Power agreement reflects current + new power through 2027