Power
48 MW
Overview
STACK SVY02A in Santa Clara on former Memorex HQ. 551,000 sqft, 48MW with dedicated substation and 8 data halls. Currently awaiting full power from Silicon Valley Power (2028 grid upgrade).
Key Points
- •551,000 sqft building with 4 floors of data halls
- •48MW capacity with dedicated on-site substation
- •8 data halls, 12MW immediately available for lease
- •Built on former Memorex headquarters site
- •Awaiting SVP grid upgrade ($450M project, completion 2028)
- •Power agreement reflects current + new power through 2027
Certifications
ISO 27001SOC 2Uptime Institute
Mar 2026
Sources: