Power
48 MW
Colocation Space
472.9K sqft
Overview
STACK SVY02 in Santa Clara on former Memorex HQ. 48MW with dedicated substation, 8 data halls. Currently awaiting Silicon Valley Power grid upgrades (expected 2028). $450M utility upgrade underway.
Key Points
- •Former Memorex headquarters in Santa Clara
- •48MW capacity with dedicated on-site substation
- •8 data halls, 564,860 sqft total (472,920 sqft data center + 87,520 sqft office)
- •4-story data center connected to 6-story ancillary building
- •Currently awaiting power: Silicon Valley Power upgrading grid
- •$450M utility upgrade expected completion 2028
Spec Sheet (PDF)
Mar 2026