Power
150 MW
Colocation Space
1.7M sqft
Overview
Microsoft's largest US data center deployment. $1.5-2B investment on 200 acres, 1.7M sq ft across 5 buildings. AI epicenter.
Key Points
- •1.7M sq ft across 5 buildings on 200 acres
- •$1.5-2B investment, largest MS deployment in US
- •4 buildings complete, 5th under construction
- •600+ employees at West Des Moines data centers
- •~70M gallons water usage in 2024
- •Microsoft's AI technology epicenter
- •New Ruthenium campus planned nearby
Development Details
Land Size
200 acres
Total Investment
$2B
Buildings (Planned)
5
Total Space (Planned)
1.7M sqft
Permanent Jobs
600
Mar 2026
Sources: