PowerHouse Charlotte
University City Boulevard, Charlotte, North Carolina
Liquid Cooling
Power
315 MW
Overview
PowerHouse's first campus outside Virginia. 122-acre site in University City, up to 5 buildings. Zoning approved Sep 2024, Q2 2027 delivery.
Key Points
- •PowerHouse's first data center outside Virginia
- •122 acres, up to 2.5M sq ft across 5 two-story buildings
- •300MW initial, expandable to 400MW
- •Zoning approved Sep 2024 (7-2 vote after concerns addressed)
- •Phase 1 site prep Q1 2025, substation Oct 2025
- •Building construction Mar 2026, all complete 2027
Development Details
Land Size
122 acres
Buildings (Planned)
5
Total Space (Planned)
2.5M sqft
Timeline
Groundbreaking:Q1 2025
First Building:Q2 2027
Mar 2026