PowerHouse Data CentersUnder Construction

PowerHouse Irving

111 Customer Way, Irving, Texas
PowerHouse Data Centers
Power

200 MW

Colocation Space

1.0M sqft

Overview

PowerHouse/Harrison Street JV in Irving-Las Colinas. 50 acres, 3 powered shells totaling 946K sq ft, 200MW. Construction early 2025, first shell late 2025.

Key Points

  • 50-acre site in Irving-Las Colinas (DFW)
  • 3 powered shell data centers, 67MW each
  • 946,000+ sq ft total, 200MW at completion
  • Adjacent to existing Oncor substation
  • Construction started early 2025, first shell late 2025
  • DFW is 2nd largest US data center market

Development Details

Land Size

50 acres

Buildings (Planned)

3

Total Space (Planned)

0.9M sqft

Timeline

Groundbreaking:early 2025
First Building:late 2025