Rowan Digital InfrastructureUnder Construction
Rowan Cinco San Antonio
TX-132 & Co Rd 683, Lytle, Texas
Power
300 MW
Overview
Rowan's first Texas hyperscale. 440 acres, $550M financing closed Feb 2025. Broke ground Aug 2025. First 60MW early 2026, full 300MW by 2027. Top 5 tech tenant.
Key Points
- •Rowan's first hyperscale campus in Texas
- •440 acres in Medina County, served by AEP
- •$550M construction financing closed Feb 2025
- •Broke ground August 2025, full operations 2027
- •First 60MW early 2026, seven buildings at full buildout
- •Tailored for Top 5 US technology company tenant
Development Details
Land Size
440 acres
Total Investment
$1B
Buildings (Planned)
7
Permanent Jobs
40
Timeline
Groundbreaking:2025-08
First Building:2026-Q1