Liquid Cooling
Power
50 MW
Colocation Space
425.5K sqft
Overview
Aligned DFW-04 in Plano partnered with Lambda for $700M AI/GPU data center. 44-acre site with 72MW buildout capacity, 425,000 sqft, construction 2024-2026.
Key Tenant: Lambda
Key Points
- •44-acre site in Plano with onsite substation
- •$700M project partnered with Lambda for AI/GPU workloads
- •72MW capacity at full buildout, first 9MW ready June 2024
- •425,000 sqft two-story building under construction
- •Aligned's proprietary air and liquid cooling technologies
- •Construction started 2024, expected completion 2026
Development Details
Land Size
44 acres
Total Investment
$1B
Total Space (Planned)
0.4M sqft
Certifications
SOC 2ISO 27001PCI DSSHIPAAHITECH
Mar 2026