DCQ

Skybox PowerCampus Texas

Wichita Falls Business Park, Wichita Falls, Texas
Skybox Datacenters
Power

300 MW

Overview

Skybox/Blue Owl partnership developing 300+ acre hyperscale campus. First building expected late 2028, up to 10 buildings at full buildout.

Key Points

  • 225-acre land purchase for $14.5M, option on additional 125 acres
  • Up to 2 million sq ft and 300+ MW across 10 buildings
  • Largest industrial announcement in Wichita Falls history
  • First 150,000 sq ft building operational by late 2028
  • Could employ ~1,000 people ($65K-$260K salaries)
  • Sub-3ms latency to Dallas Infomart

Development Details

Land Size

300 acres

Buildings (Planned)

10

Total Space (Planned)

2.0M sqft

Permanent Jobs

1.0K

Timeline

Land Acquired:2026-02
First Building:2028