Power
240 MW
Colocation Space
1.4M sqft
Overview
Stream's second Wilmer campus (DFW C). 140 acres, 240MW with 372MW Oncor substation. $300M new building filed Sep 2025. First campus (77 acres) fully leased.
Key Points
- •Second Wilmer campus (DFW C): 140 acres, 1.4M sq ft, 240MW
- •372MW Oncor substation planned on-site
- •$300M new building (48MW, 360,750 sq ft) filed Sep 2025
- •Construction Apr 2026 - Oct 2027, Gensler design
- •First Wilmer campus (DFW B, 77 acres, 90MW) fully leased
- •Apollo acquiring majority stake in Stream (2025)
Development Details
Land Size
140 acres
Total Investment
$0B
Total Space (Planned)
1.4M sqft
Timeline
Groundbreaking:2026-04
First Building:2027-10
Mar 2026
Sources: