Power Density
22 kW/rack
Overview
First data center on NTT's 78-acre, 224 MW Ashburn campus in Data Center Alley with conflicting power capacity reports ranging from 12.6-20 MW.
Key Points
- •First of nine planned facilities on NTT's 78-acre Ashburn campus with 224 MW total capacity
- •Critical IT load of 12.6 MW according to official NTT sources, though third-party reports vary up to 20 MW
- •Power densities up to 22 kW per rack with N+2 distributed redundancy per vault
- •Located in Ashburn's Data Center Alley with below-national-average utility rates from Dominion Virginia Power
- •Features 34.5kV electrical distribution and on-site generators for 24-hour full-load runtime
Certifications
ISO 27001SOC 1SOC 2PCI DSS
Infrastructure
Cooling Redundancy
N+2
Spec Sheet (PDF)