Liquid Cooling
Power
900 MW
Overview
145-acre I-95 corridor campus. Broke ground July 2024, first 150MW expected Q4 2025.
Key Points
- •145-acre site along I-95 corridor in Spotsylvania County
- •Land acquired January 2024, broke ground July 2024
- •Up to 800-900MW via three 300MW substations
- •First 150MW phase due Q4 2025
- •Up to eight 2-3 story buildings, 3.5M sqft total
- •Phased deliveries Q3 2025 through Q4 2027
- •Offers competitive advantage in power-constrained NoVA market
Development Details
Land Size
145 acres
Total Space (Planned)
3.5M sqft
Timeline
Initial Phase:Q4 2025
Full Buildout:Q4 2027
Mar 2026