VantageUnder Construction

Cyberjaya II (MY2)

Cyberjaya, Cyberjaya, Malaysia
Vantage Data Centers
Power

436 MW

Colocation Space

4.8M sqft

Overview

The KUL2 campus is sited on 52 acres adjacent to Vantage's flagship Malaysia campus and will include 6 data centers when fully developed.

Key Points

  • 52 acre (21 hectare) campus that will include 6 data centers
  • 436MW of critical IT load capacity when fully developed
  • 4.8M square feet (445K square meters) of total space
  • N+1 substation on campus at 500MVA with power provided by Tenaga Nasional Berhad (TNB)
  • Will use closed-loop chilled water system with Water Utilization Efficiency (WUE) near zero

Development Details

Total Investment

$3B

Timeline

First Building:Q4 2025

Infrastructure

UPS Redundancy

N+1

Cooling Redundancy

N+1 overall, N+2 component-level redundancy across mechanical systems

Security

24x7x365 securityCCTV surveillanceTwo-factor door access controlPerimeter security gates and fencingVisitor management system