Power
75 MW
Colocation Space
500.0K sqft
Overview
Part of EdgeCore's expanding Mesa campus. Campus grew from 40 to 84 acres in 2025, capacity from 200MW to 450MW+.
Key Points
- •Part of 84-acre Mesa campus
- •Campus expanded to 450MW+ capacity in 2025
- •PH01 operational, PH02-03 under construction
- •Salt River Project power supply
Certifications
SOC 2ISO 27001Green GlobesLEED
Mar 2026