Power
192 MW
Colocation Space
1.5M sqft
Overview
The OH1 campus in New Albany, Ohio spans 70 acres and will house three two-story hyperscale data centers with the first building slated to be operational by December 2025.
Key Points
- •70 acre campus that will house three two-story hyperscale data centers
- •192MW of critical IT load across 1.5 million square feet
- •First building slated to be operational by December 2025, with additional phases through 2028
- •Located just 20 minutes away from downtown Columbus
- •Each data center is being built to LEED Silver standards
Development Details
Land Size
70 acres
Total Investment
$2B
Buildings (Planned)
3
Total Space (Planned)
1.5M sqft
Timeline
Groundbreaking:2024-10-25
First Building:December 2025
Certifications
LEED Silver
Infrastructure
UPS Redundancy
N+1
Cooling Redundancy
N+2
Security
24x7 securityCCTVBiometricPerimeter security gates and fencingDual authentication