Power
300 MW
Overview
CloudHQ's MDC campus in Manassas. 300MW across 3 buildings (84MW each). Connected to Manassas Fiber Highway.
Key Points
- •300MW total capacity
- •3 buildings: MDC1, MDC2, MDC3
- •Each building: 84MW, 599,198 sq ft
- •Two on-site substations
- •MDC1 ready in <22 months from commitment
- •Connected to Manassas Fiber Highway
Spec Sheet (PDF)
Mar 2026
Sources: